Core Refusal Reason
The application for an extension of duration was refused because no substantial works had been carried out on the site during the lifetime of the parent permission, failing to meet the mandatory requirements of Section 42(1)(c)(ii) of the Planning and Development Act 2000-2023.
Decision Maker's Conclusion
- A site inspection confirmed that the development permitted under Pl. Ref. 21/625 has not yet commenced and the site remains a greenfield in agricultural use.
- The applicant failed to satisfy the statutory requirement under Section 42(1)(c)(ii) of the Planning and Development Act 2000-2023, which stipulates that substantial works must be carried out during the duration of the permission.
- As no substantial works were performed, the Planning Authority is legally precluded from extending the appropriate period of the planning permission.
Cited Policies (CDP)
Decision Document Summary
This application sought a three-year extension of duration for a previously granted permission (Pl. Ref. 21/625) for a two-storey dwelling, private well, and wastewater treatment system at a greenfield site in Pluckstown, Athboy, Co. Meath. Upon inspection, the Planning Authority determined that the development had not yet commenced due to the applicant's personal and financial matters. The application was refused because it failed to comply with Section 42 of the Planning and Development Act 20...SOURCE PDFOpen Original