D26A/0376/WEB

The development will consist of the following:1) the construction of 1 no. detac

Refused

Core Refusal Reason

The proposal was refused due to its premature nature regarding infrastructure dependency, non-compliance with road safety objectives for Brennanstown Road, and an unacceptably low residential density for the area.

Decision Maker's Conclusion

  • The development is considered premature as it relies on third-party lands for vehicular access, fire safety, and water services, creating an uncertain and unsatisfactory development pattern.
  • The proposal violates Specific Local Objective 73, which seeks to limit development along Brennanstown Road to improve safety, making the application contrary to the proper planning of the area.
  • The proposed density of 6.7 units per hectare is significantly below the required 40-80 dph range for suburban extensions, representing an unsustainable use of serviced land and setting an undesirable precedent.

Cited Policies (CDP)

Zoning Objective ‘A’Section 12.4SLO 73Policy Objective PHP18Section 4.3.1Section 12.3.3.2

Decision Document Summary

The application proposed the construction of a detached dwelling on a site located south-east of Eski Shehr, Brennanstown Road, Cabinteely. The Planning Authority refused permission primarily because the development's access and essential services were dependent on future development on adjacent lands, rendering the project premature. Furthermore, the proposal conflicted with Specific Local Objective 73 regarding road safety and failed to meet the minimum residential density standards of 40-80 u...
SOURCE PDFOpen Original
Note: If code appears below, the council site is blocking the preview. Please open the original file.

PDF Document Missing

The original decision document for this case could not be linked. This often happens for older cases or those with restricted documentation.