F26A/0572E

The development will consist of Retention of existing building which c

Refused

Core Refusal Reason

The development was refused due to insufficient environmental assessments (Appropriate Assessment and Flood Risk), inadequate wastewater and drainage proposals, and the failure to maintain a mandatory 10-meter buffer from a watercourse.

Decision Maker's Conclusion

  • The absence of a Screening for Appropriate Assessment means the Planning Authority cannot rule out significant adverse effects on the North-West Irish Sea SPA (004236) via the Bracken River.
  • The lack of adequate wastewater treatment, surface water drainage, and flood risk assessments poses a risk to public health and the Bog of the Ring groundwater drinking water protection zone.
  • The development is located within 10 meters of a watercourse, failing to provide the necessary riparian buffer required by the Fingal Development Plan 2023-2029.

Cited Policies (CDP)

Objective DMSO1Policy GINHP19Objective DMSO160Objective DMSO203Objective DMSO212Objective DMSO215Objective IUO16Objective DMSO154Objective DMSO156Objective DMSO210Objective IUO26

Decision Document Summary

This application sought the retention of an existing building at Ring Commons, Naul, Co. Dublin. The local authority refused the proposal because the applicant failed to provide essential technical documentation, including an Appropriate Assessment screening and a Flood Risk Assessment. Additionally, the development's proximity to the Bracken River violates mandatory environmental buffer zones, and the lack of robust drainage and wastewater solutions was deemed prejudicial to public health and t...
SOURCE PDFOpen Original