Core Refusal Reason
The application failed to meet statutory requirements for an extension of duration as the permitted development had not commenced and no substantial works had been carried out on-site.
Decision Maker's Conclusion
- The development permitted under planning reference 19/491 has not commenced on the site to date.
- No substantial works were carried out pursuant to the original permission during its appropriate period.
- The application fails to meet the mandatory requirements of Section 42(1)(a)(iii) of the Planning and Development Act 2000 (as amended) for granting an extension of duration.
Cited Policies (CDP)
Decision Document Summary
This application sought a three-year extension of duration for the construction of two light industrial/warehousing units at the Kilmallock Road Enterprise Centre, Co. Limerick. The local authority refused the request because the applicant confirmed that no works had commenced on-site. Under Section 42 of the Planning and Development Act 2000, an extension cannot be granted if substantial works have not been carried out prior to the expiration of the original permission....SOURCE PDFOpen Original