F26A/0016E

Temporary Permission for a period of 5 years at this site (c. 1.1 Ha),

Refused

Core Refusal Reason

The proposed development conflicts with the delivery and construction phase of the Metrolink project.

Decision Maker's Conclusion

  • The subject site is located on lands specifically required to facilitate the delivery of the Metrolink project as approved under ACP Case Reference 314724.
  • Permitting the development would be prejudicial to the construction phase of the Metrolink project at this location.
  • The proposal is contrary to the Fingal Development Plan 2023-2029 and the proper planning and sustainable development of the area.

Cited Policies (CDP)

Policy CSP29Objective CMO23

Decision Document Summary

The applicant sought temporary five-year permission for a development on a 1.1-hectare site at Swords Pavilions, Malahide Road, Swords. The local authority refused the application because the lands are identified as necessary for the delivery of the Metrolink project, which has been approved by An Coimisiún Pleanála. The planning authority determined that the development would interfere with the construction phase of this strategic transport infrastructure, thereby violating Policy CSP29 and Obj...
SOURCE PDFOpen Original