268343
the construction of single storey pavilion and pier wall consisting of public changing facilities, a public communal space, a lifeguard station and lifeguard WC and all ancillary site works. Provision of 1x no. UA parking space, 2x no. unmarked public parking spaces, vehicular ramp, planters and wastewater holding tank to pier. Remedial works to the pier including repointing of pier flagstones, canted pier wall and cut stone steps. Partial demolition of the southern pier wall limited to the 20th century element. Demolition of modern concrete step to access route of northern steps of pier. Removal of modular building and relocation of Shannon Commissioners stone. This Part 8 contains works to a protected structure RPS: 515, NIAH Reg No. 21900901