Core Planning Reasoning
The Inspector recommended that the Board dismiss the appeal under section 138(1)(a)(i) of the Planning and Development Act 2000, as the appeal was made without any specific supporting arguments or evidence and was therefore considered to be without substance.
Decision Maker's Conclusion
- The appellant failed to state full grounds of appeal or provide supporting reasons, considerations, or arguments regarding how the development failed to accord with proper planning or sustainable development.
- The appellant put forward no information or justification to demonstrate how the submitted Environmental Impact Assessment Report (EIAR) or the Appropriate Assessment (AA) process was defective.
- The appeal does not meet the requirements of section 127(1)(a) of the Act and should be dismissed as being without substance.
Cited Policies (CDP)
Donegal County Development Plan 2018 to 2024Policy NH-P-7Section 8.1Policy EX-P-1Policy EX-P-2Policy EX-P-3Policy EX-P-4Policy EX-P-5Policy EX-P-6Policy NH-P-1
Decision Document Summary
The proposal involves a 25-year permission for rock extraction and blasting within a new 3.0ha area, the relocation of a stone crushing plant, and associated works at an existing quarry site in Carrownamaddy, Co. Donegal. The 14.67ha site is located in an area of Moderate Scenic Amenity near Muckish Mountain and sensitive ecological designations including the Muckish Mountain SAC and Derryveagh and Glendowan Mountains SPA. The Planning Authority had initially granted permission subject to 19 con...SOURCE PDFOpen Original