Infrastructure upgrade works to include the construction of an above ground 790cu.m mains-fed circular galvanised, butyl lined steel firewater supply tank, a pumphouse and associated pipework to supply sprinkler systems and site fire hydrants and the construction of a new 2,000cu.m firewater retention pond, associated pipework and a control building with associated site works which includes installation of berms and a new 2.4m high palisade fencing. This application relates to an which has an Industrial Emissions License (PO091-02). A Natura Impact Statement will be submitted to the planning authority with the application.
Granted
Analysis not available for this case.
Decision Document Summary
No text availableSOURCE PDFOpen Original