Core Refusal Reason
The Inspector recommended granting permission, overturning the Planning Authority's refusal, on the grounds that the 36m mast is technically necessary for 4G/5G coverage and its visual impact is localized and acceptable given the presence of similar existing infrastructure nearby.
Decision Maker's Conclusion
- The proximity to residential dwellings and potential public health concerns are not valid planning issues as they are regulated by separate codes and licenses.
- The applicant provided sufficient technical justification demonstrating that the existing water tower is unsuitable for necessary 4G and 5G upgrades due to space and placement issues.
- The development is consistent with national policy to facilitate high-capacity telecommunications and would not significantly injure the visual or residential amenities of the area.
Cited Policies (CDP)
Objective TC01Objective TC02Objective TC03Objective TC04Objective TC05Section 9.3Section 9.3.1Section 18.26
Decision Document Summary
The proposal involves the erection of a 36m-high telecommunications mast and associated equipment on a 0.09-hectare site at Waddingsland, Rosslare Harbour, Co. Wexford. The site is an irregular agricultural plot located near existing and planned residential estates. Wexford County Council initially refused permission based on the presumption against masts in proximity to residential areas and a perceived lack of justification for a new site instead of co-locating on a nearby water tower. On appe...SOURCE PDFOpen Original
Note: If code appears below, the council site is blocking the preview. Please open the original file.