211918
a Solar PV Energy Development with a total site area of 23.58 ha, to include solar panels mounted on steel support structures, associated cabling and ducting, 5 No. MV Power Stations, 1 No. Client Substation, 1 No. Temporary Construction Compound, access tracks, hardstanding area, boundary security fencing and security gates, CCTV, landscaping and ancillary works. Significant further information/revised plans submitted on this application
Core Planning Reasoning
The development is recommended for grant as it complies with European, national, and local policy frameworks for renewable energy. The Inspector found that the proposal would not significantly impact visual or residential amenities, traffic safety, or the integrity of Natura 2000 sites, and represents a sustainable use of rural land compatible with the Meath County Development Plan.
Decision Maker's Conclusion
- The development is in accordance with European, national, and regional renewable energy policies and the specific provisions of the Meath County Development Plan 2021-2027.
- The proposal would not seriously injure the visual or residential amenities of the area, nor would it interfere with protected views, archaeological heritage, or landscape character.
- The project is acceptable in terms of traffic safety, glint and glare, and flood risk, and will not have a significant adverse effect on any European site or local ecology.