Planning permission for the development will consist of the refurbishment and extension of the buildings comprising: 1) reconfiguration of the layout of the basement to provide for 16 no. car parking spaces (including 1 no disabled car parking space); 174 no. cycle parking spaces; 2 no. motorcycle parking spaces; staff showers, changing rooms and lockers; bicycle repair area; plant and tank areas and bin storage areas; 2) reconfiguration of the existing office floorplates and construction of extensions on the eastern and western sides of the buildings at first, second, third, fourth and fifth floors to provide an additional 6,239 sq. m. GFA of office accommodation (to 16,111 sq. m. GFA) including office space for collaborative working at ground floor in Hardwicke House and an ESB substation and switchrooms at ground level; 3) construction of two additional setback floors resulting in an eight storey Hardwicke House, setting back to a seven storey Montague House; 4) removal of all existing external cladding and replacement with a new stone frame structure framing double height glazed openings; 5) provision of roof terraces at sixth and seventh floor level on Montague House and at the sixth floor level on Hardwicke House; 6) provision of a 541 sq. m. plant area enclosure and 85 sq. m. solar photovoltaic ('PV') modules at roof level; 7) upgrading of pedestrian route along the eastern boundary, reconfiguration of the disabled ramp and widening of the access steps to the front of Hardwicke House.

Granted

Core Planning Reasoning

The development represents an acceptable quantum and quality of development in an accessible urban location, is consistent with the Z6 zoning and SDRA 18 objectives, and successfully balances city-centre intensification with the protection of surrounding residential and heritage amenities.

Decision Maker's Conclusion

  • The proposed height, scale, and massing are consistent with the 9-storey limit set for SDRA 18 and provide an appropriate transition between the modern commercial developments to the west and the historic Georgian core to the east.
  • Daylight and sunlight impacts on neighboring residential and commercial properties are within acceptable limits for a dense inner-city context and comply with the flexible interpretation of BRE guidelines.
  • The development appropriately supports sustainable travel patterns by significantly reducing car parking provision and enhancing pedestrian permeability and cycle infrastructure at a location well-served by the LUAS and bus networks.

Cited Policies (CDP)

Zoning Z6 (Employment/Enterprise)SDRA 18 (National Concert Hall Quarter)Section 4.5.4.1 (Approach to Taller Buildings)Policy SC7Policy SC16Policy SC17Policy SC28Policy CEE1Policy CEE3Policy CEE4Policy CEE5Policy CEE11Policy CHC1Policy CHC2Policy CHC4Section 16.2 (Design, Principles & Standards)Table 16.1 (Car Parking Standards)Table 16.2 (Cycle Parking Standards)

Decision Document Summary

The proposal seeks the refurbishment and extension of two conjoined office buildings, Montague House and Hardwicke House, adding two setback floors to reach a maximum of 8 storeys. The 0.3084ha site is situated in the National Concert Hall Quarter (SDRA 18), a transitional zone between modern high-density offices and the historic South Georgian core. While Dublin City Council granted a 5-year permission, the applicant appealed for a 10-year term due to lease complexities; however, the Inspector ...
SOURCE PDFOpen Original
Note: If code appears below, the council site is blocking the preview. Please open the original file.

PDF Document Missing

The original decision document for this case could not be linked. This often happens for older cases or those with restricted documentation.

View the appeal at An Bord Pleanála