Core Refusal Reason
The application was refused due to inadequate information regarding traffic safety, flood risk, and environmental impact thresholds, as well as prematurity pending the regularisation of unauthorised site works.
Decision Maker's Conclusion
- The applicant failed to demonstrate safe access arrangements and required sightlines for the R772-17 and L5078, rendering the proposal prejudicial to traffic safety.
- Insufficient data was provided regarding infill volumes and depths, creating uncertainty over flood risk impacts and whether the development triggers a mandatory Environmental Impact Assessment Report (EIAR).
- The proposal is considered premature until existing unauthorised developments and works on the subject lands are regularised.
Cited Policies (CDP)
Decision Document Summary
The proposal sought permission to import soil onto existing lands at GoreyCorporationLands, Gorey Urban, for the purpose of land maximisation. The local authority refused the application on three main grounds: traffic safety concerns arising from inadequate sightlines and access details on a Class 1 Regional Road; a lack of technical clarity regarding infill volumes which prevented a proper assessment of flood risks and EIA requirements; and the presence of unauthorised works on-site. Consequent...SOURCE PDFOpen Original